philippi Academy · Distribute and Secure

Plan PSU 9012-8: Distribute outputs to loads

6 min readBy Michael KögelLast reviewed

In short

The PSU 9012-8 ADV has eight channels, handles a total current of 70 A continuously (90 A for one minute) and up to 20 A per output, up to 25 A on outputs 7 and 8. Planning is done in this order: first the number of channels, then the realistic simultaneity case against the 70 A, and finally the largest single consumer per channel, including inrush current. Special cases such as dimmable circuits and H-bridge outputs are planned first.

The PSU Switching Unit 9012-8 ADV has eight inputs and eight outputs, handles a total current of 70 amps continuously (90 amps for one minute) and up to 20 amps per channel, up to 25 amps on outputs 7 and 8. These three figures determine the entire planning — and they are regularly considered in the wrong order.

The three limits and their hierarchy

With a digital switching module, there are three upper limits that must be observed simultaneously:

  • Channel current. Up to 20 A per output, up to 25 A on outputs 7 and 8. The largest individual consumer on a channel must remain below this — including its inrush current. Loads above 20 A therefore belong on output 7 or 8.
  • Total current. 70 A continuously across all channels, 90 A for one minute. Six channels at 20 A and two at 25 A theoretically yield 170 A; this scenario is not intended and does not need to be.
  • Number of channels. Eight outputs. In practice, this is the limit you encounter first.

The correct order for planning is precisely the opposite of intuition: first the number of channels, then the total current, and finally the channel current. This is because the number of circuits is fixed at the beginning, while the currents can still be distributed.

For 24 V systems there are the 5024-8 ADV with 50 A total current and 5 to 15 A per output, and the 10024-8 ADV with 100 A and 5 to 30 A per output. Planning follows the same order, just with different limits.

Concurrency instead of addition

The 70 A continuous current is no cause for concern, as long as you calculate realistically. The decisive factor is not the sum of all connected consumers, but the sum of those that run simultaneously.

An example from an expansion: Four dimmed lighting circuits at 10 A each, a reading lamp at 10 A, a cool box at 15 A, a switched inverter release circuit, and a continuous positive feed at 5 A. On paper, this adds up to around 70 A — in reality, the lighting circuits rarely run simultaneously at full brightness, and the cool box cycles.

Therefore, the planning parameter is the realistic concurrency case, not the theoretical maximum. If you still want to be safe, plan for the worst realistic case: the evening when all the lights are on, the cooling is running, and the pump starts. Short peaks are covered by the 90 A reserve for one minute; the continuous limit is 70 A.

Assigning consumers to channels

Two principles have proven effective.

Group by function, not by location. Everything that is switched on and off together belongs to one channel. Everything that needs to be switched independently requires its own channel. The most common planning mistake is to combine two circuits that later need to be operated separately — and the realization comes after installation.

Set the special cases first. Outputs with special requirements — dimmable, motor control via H-bridge, continuous positive without shutdown — are planned first. The simple on-off circuits can then be fitted anywhere.

NoteThe inputs are permanently assigned to the outputs: input 1 belongs to output 1 and so on. When planning the buttons, it is worth considering this assignment from the beginning, instead of trying to find it later.

An assignment to write down

The assignment belongs in a table before the first cable is laid. Four columns are sufficient: channel, consumer, current limit, function.

Its usefulness only becomes apparent later. A digital switching module has no labeled fuses that would indicate what goes where — the assignment exists in the configuration and in the mind of the person who made it. A printed table in the technical cabinet is therefore not bureaucracy, but a substitute for the labeling that used to be on the fuse holder.

Plan for reserve

Eight channels sound like a lot and are quickly occupied during expansion. A channel that remains free is therefore not a waste, but the only reserve that can be used without modification.

If the system expands beyond eight circuits, multiple units can be operated in series or parallel. This is the cleaner way — cleaner, at least, than putting two consumers on one channel that really belong separately.

Check before installation

  • Each channel has exactly one purpose and this purpose is noted.
  • The largest consumer per channel, including inrush current, is below 20 A, below 25 A on outputs 7 and 8.
  • The realistic concurrency case remains below 70 A.
  • Dimmable circuits are planned as such — not every consumer tolerates dimming.
  • At least one channel is free or expansion is planned.

Typical planning errors

  • All currents added up. Leads to the conclusion that the module is too small — although the real concurrency case is far below.
  • Inrush current forgotten. Pumps and compressors draw multiple times their continuous current at startup.
  • Two circuits on one channel. Saves an output but costs separate operability.
  • No assignment table. Without it, the assignment can be reconstructed after two years, but only with difficulty.
  • All eight channels occupied. The first additional consumer then forces a replanning.

· Managing Director, philippi elektrische systeme GmbH

Michael Kögel is Managing Director of philippi elektrische systeme GmbH in Remseck am Neckar. Since 1978, the family-owned company has developed and manufactured on-board electrical systems for yachts, motorhomes and special vehicles.

Diplom-Ingenieur (Dipl.-Ing.), electrical engineering, with philippi for more than 35 years. Articles in the philippi Academy are written together with the engineering department and technically reviewed.

Published · Last reviewed

Frequently asked questions. Answered briefly.

Can I load all eight channels to the maximum?

Mathematically that would be 170 A — six outputs at 20 A and two at 25 A — but the total current is 70 A continuous and 90 A for one minute. This case is not intended, nor does it need to be. What counts is the realistic simultaneity case: the sum of the loads that actually run at the same time, not the sum of all connected ones.

What happens when eight channels aren't enough?

Several PSU units can be operated in series or in parallel. That is the clean way — cleaner than putting two loads on one channel that are meant to stay separately controllable. Group by function: whatever is switched together belongs on one channel, everything independent needs its own.

Do I need to include the inrush current in the calculation?

Yes. Pumps and compressors draw a multiple of their continuous current when starting. This peak value, not the operating current, determines the channel choice. Outputs 1 to 6 can carry up to 20 A, outputs 7 and 8 up to 25 A; the set current limit must let the start-up peak through and still stay below the cable's current-carrying capacity.

Technical

Your case isn't covered?
Ask us.

Our team knows every component and usually replies on the same working day, by email or by phone.

philippi tote bag and catalogue