13 min read
Answered briefly

Eight steps in a fixed order: inventory, determine consumption, design storage, design sources, plan distribution, install measurement technology, convert and test, document. Steps two to five are done at the desk — only then are orders placed. For connection technology, fusing, and mechanics, an additional quarter to a third is added to the main components, and each stage ends in an operational state.

A vehicle electrical system refit rarely fails due to technology and almost always due to the sequence. Each step provides the input for the next – skipping a step replaces it with an estimate and carries that error all the way to the end.

The Eight Steps

The first five steps cost nothing but time at a desk. That's precisely what makes them unpopular – and that's precisely where it's decided whether the conversion happens once or twice.

Step Result Effort
1 · Inventory List of all components with condition and decision half to full day
2 · Determine Consumption Daily balance in ampere-hours one evening, with measurement one week
3 · Design Storage Capacity, technology, installation location one evening
4 · Design Sources Charging power from alternator, solar, shore power one evening
5 · Plan Distribution Sketch with circuits, cross-sections, fuses one to two evenings
6 · Set Up Measurement Technology List of measurement points one hour
7 · Convert and Test Completed system with measurement protocol the actual conversion
8 · Document Plan, labeling, photos half day, parallel to conversion

The time estimates apply to a manageable system. For multiple battery banks, AC side, and bus system, they tend to double.

Step 2 is the Most Important

The consumption balance determines everything else: the size of the battery bank, charging power, cross-sections, and ultimately the budget. Nevertheless, it is most often skipped because it is laborious and produces no physical part.

It is established per consumer with three pieces of information: current consumption, operating hours per day, and whether it runs while driving or while docked. The distinction is important because the two cases place different demands – while driving, the alternator charges, while docked, only what is in the battery bank counts.

NoteIf you already have a shunt, you save yourself the calculations: one week of operation with recorded consumption is more accurate than any table. If you don't have one, you should plan for it anyway – then the figures will be available next time.

The result includes a surcharge. Experience shows that consumers are added during operation that were not included in the planning. Twenty to thirty percent reserve on the calculated daily balance is not a luxury, but the difference between a system that fits and one that you have to revisit in two years.

Budget: Where the Money Really Goes

The surprise in the cost plan is rarely the major components. Batteries, charge controllers, and monitors have fixed prices and are correctly accounted for. What is underestimated is the rest.

  • Cables and cable lugs. Large cross-sections are expensive, and more is always needed than measured – cable runs are not straight.
  • Connection technology. Busbars, through-hull fittings, terminal blocks, fuse holders: individually inconspicuous, but collectively a separate item.
  • Fuses. Main fuses near the battery, fuses per circuit, plus the appropriate holders.
  • Tools. A proper crimping tool for large cross-sections is not an option, but a prerequisite.
  • Mechanics. Battery mounts, through-hull fittings, cable ducts, fastening material.

As a rule of thumb: For connection technology, fusing, and mechanics, an additional quarter to a third is added to the sum of the main components. If this is not planned for, you will have to reorder in the middle of the process – and wait.

Time: What Makes the Plan Fail

The schedule almost never breaks due to the work itself, but due to three other things: delivery times, accessibility, and what is revealed when opened.

To combat delivery times, ensure everything for a stage is completely present before it begins. Nothing helps with accessibility except a realistic assessment: pulling a cable through an existing cable duct takes many times longer than the same meter in new construction. And only a buffer helps against the third point.

WarningA refit should never be planned so that the vehicle or boat absolutely must be operational at the end of the stage. This very pressure creates the temporary solutions that remain for ten years.

In Stages Instead of One Go

Few refits are completed in a single weekend. Sensibly cut stages each end in an operational state – not in the middle of distribution.

  1. Stage A: Storage and Supply Line. Battery bank, main switch, main fuse, busbars, shunt. After this, the system runs as before, but on a clean basis.
  2. Stage B: Distribution. Switch panel, fuses per circuit, re-routing of consumers. This is where the actual order is established.
  3. Stage C: Sources. Charge booster, solar, shore power – whatever is added depends on the already completed distribution.
  4. Stage D: Monitoring and Comfort. Additional measurement points, display, remote access.

The advantage of this division is not only organizational. After each stage, it is possible to measure whether the result is correct – and an error remains confined to one stage.

Test Before Closing

At the end of each stage, a brief test is conducted before panels are reinstalled. Useful checks include: voltage at the battery bank and at the furthest consumer under load, checking all fuse sizes against the plan, visual inspection of all terminals for secure fit and strain relief, and a look at the heating after one hour of full load.

The values should be noted. They serve as a reference against which any changes can be compared in three years – without them, any subsequent troubleshooting starts from scratch.

Typical Mistakes

  • Starting with the order. Without a consumption balance, the size of the battery bank is guessed.
  • Not including a surcharge. Neither for consumption, nor budget, nor time.
  • Stages cut incorrectly. A stage must end in an operational state.
  • Forgetting small parts. Connection technology and fusing are a separate cost block.
  • Working under time pressure. Temporary solutions from the last evening last the longest.
  • Closing before testing. Afterwards, every correction costs ten times as much.

If you are unsure about the design, you should have the balance reviewed before ordering. Our team checks consumption balances and distribution plans – in a consultation or via the contact form.

FAQ

Frequently Asked Questions

Where do I start with the refit?

With the inventory and the consumption balance—not with the purchase. Steps two to five are done at the desk and provide the input variables for everything else. Anyone who skips them will build twice.

A quarter to a third. Cables, cable lugs, busbars, fuse holders, tools, and mounting materials are individually inconspicuous but collectively a separate item – one that forces reordering in the middle of a conversion.

So that each ends in an operational state: first storage and supply, then distribution, then sources, finally monitoring and comfort. After each stage, it can be measured whether the result is correct.

Fitting for the topic

Suitable Products

Entwicklung philippi — Entwicklungsabteilung, philippi elektrische systeme GmbH

Verfasst und fachlich geprüft von der Entwicklungsabteilung der philippi elektrische systeme GmbH in Remseck am Neckar. Ändert sich eine Norm oder eine Produktspezifikation, wird der Beitrag überarbeitet und das Prüfdatum aktualisiert.